This April is the last month I worked with Patimban. A lot memory happen from beginning it was a sea the continue to build couseway. Piling at couseway form one pier to ther pier, test pile PDA test and PIT and also start excavation. Also don't forget to drilling test in bagan at sea. In Patimban I meet 3 japanese people Atsutsi Kawamura, besso and Tishiko Nishio 1. Drilling at sea Began in April 2021 and ended at June 2021. Firstly we place bagan at sea according the coordinate. then continue mobilize the drilling machine. A lot problem happen like like sea tide, difficult to move drilling machine from one bagan to other bagan, machine broken and a lot more. From Abutment one to pier 24 about 1 km. 2. Ramp ON Ramp OFF We built a road in swampy area about 500 m from existing road which built with pile slab in Packet 4. First install bamboo deep about 5 m then continue with matras bamboo then geotextile next embakment about 1 - 3 m. 3. PDA ...